Project
Engineering Design & Construction Supervision Services for the Reconstruction of Zahrani Bridge – Coastal Road Zahrani Interchange: Kinnareet Overpass, Ghazieh Overpass, Rmeileh Overpass, Wardaniyeh Overpass
Client
Council for Development and Reconstruction (CDR) – Hariri Foundation
Associated Firm
Location
Lebanon
Type
Engineering
Sectors
Transportation & Highway
Date
Oct, 2006 – May, 2007
Project Details

Narrative Description of Project:

A number of bridges on the Lebanese territory were a target during the Israeli hostilities of July-August 2006. The resulting damages were classified into the following. This project involves six of those bridges along the South Motorway.

Description of Actual Services Provided:

The Scope of work has been determined according to the structural and laboratory reports on each of the damaged bridges. A solution was formulated for each and re-construction was supervised accordingly.
The Consultant (TEAM International) has transmitted to the Contractor the as-builts provided by the CDR for each of the bridges below. 

The scope of work was determined as follows:

1) Rmeileh / Wardaniyeh PS-4 Demolishing & total reconstruction
2) Rmeileh Village PS-5 Demolishing & total reconstruction
3) Ghazihey Village PS-14 Rehabilitation & jacketing of piers
4) Ghazieh /Kinnareet PS-15 Jacketing of pier & reconstruction of overpass slab
5) Zahrani Interchange Demolishing & total reconstruction
6) Zahrani Multiple-Box-Culvert Demolishing & total reconstruction