Supervision Of Two Water Projects For UNICEF
Project | Supervision Of Two Water Projects For UNICEF
|
Client | UNICEF – Beirut
|
Associated Firm | – |
Location | Lebanon
|
Type | Engineering
|
Sectors | Water, Wastewater and Dams
|
Date | 1991 – 1992
|
Project Details
Work involved supervision and contract administration of two water projects for the villages of Toura and Maarakeh, Sour Water Authority. The projects consisted of equipping wells, construction of pump house and laying of pipes as follows:
– Water well depths 235m and 350m, diameter 12″
– Equipping wells by electric submersible pumps 100 HP and 150 HP with Total Manometric Head of 310m.
– Rehabilitation/construction of pump houses
– Laying of new pipelines using 5″ and 6″ galvanized steel pipe